Hydro-Sherbrooke or Hydro-Québec: who is my utility, and what it changes

In the Eastern Townships, your electricity comes from Hydro-Québec… or not. Sherbrooke has its own network, Hydro-Sherbrooke, serving part of the city; Magog and Coaticook also have municipal networks. Your utility’s name is on your bill, and it changes the steps for a new service entrance or an outage.

French version reviewed by William Letendre, master electrician, on October 21, 2026

In short

  • Your utility’s name is on your electricity bill.
  • In Sherbrooke, Hydro-Sherbrooke serves part of the city and Hydro-Québec the rest; Magog and Coaticook have municipal networks.
  • During an outage, call the right network: Hydro-Sherbrooke at 819 821-5728, Hydro-Québec at 1 800 790-2424.
  • For a Hydro-Sherbrooke connection, the subscription is requested at least seven business days ahead, and the master electrician sends the work declaration.
  • LogisVert, Hydro-Québec’s heat pump program, is also open to municipal network customers.
In this guide
  1. How to tell
  2. What it changes
  3. Who to call
  4. In the Eastern Townships
  5. A connection with Hydro-Sherbrooke
  6. Programs
  7. What we do for you

How to tell

Look at your electricity bill: the utility’s name is on it. In Sherbrooke, part of the city is served by Hydro-Sherbrooke, a city service, and the rest by Hydro-Québec. Magog and Coaticook each have their own municipal network. Elsewhere in the Eastern Townships, it’s Hydro-Québec.

What it changes

  • A new service entrance, or a 200 A upgrade. The supply request, shutoff and reconnection are done with your utility, according to its technical requirements and timelines. We handle it with you.
  • An outage. You have to call the right network. For Hydro-Sherbrooke, the official outage page shows current interruptions and the number to report one (819 821-5728 according to the city’s website).
  • Programs. Some Hydro-Québec programs are for its own customers; others accept municipal networks. We check what applies to you before bringing it up.

Who to call

UtilityWhereOutages
Hydro-SherbrookePart of Sherbrooke819 821-5728, 24 hours a day
Hydro-MagogMagog (municipal network territory)819 843-3333; evenings, 819 843-3334
Hydro-CoaticookCoaticook (town network)819 849-6331
Hydro-QuébecEverywhere else in the Eastern Townships1 800 790-2424

Our Power outage page brings these numbers together, with the online outage maps and safety instructions. A wire on the ground or a burning smell: call 911.

In the Eastern Townships

  • Sherbrooke: Hydro-Sherbrooke in part of the city, Hydro-Québec elsewhere.
  • Magog: the City of Magog’s municipal network.
  • Coaticook: the City of Coaticook’s municipal network.
  • Elsewhere in the Eastern Townships: Hydro-Québec.

A connection with Hydro-Sherbrooke

  1. You submit the subscription request at least seven business days before the date you want, online or through customer service (819 821-5622), with the exact address clearly visible on the house.
  2. The master electrician sends the work declaration as soon as the installation is compliant; above 200 A, they also send a description of the loads.
  3. Hydro-Sherbrooke connects within seven business days, in a normal situation: under 200 A, a connection within 30 m of the network and a cleared corridor.

At Hydro-Québec, only CMEQ members can send the work request. For choosing between an overhead and an underground service, see Underground or overhead service entrance.

Programs

Hydro-Québec’s LogisVert heat pump program is open to homeowners, including Hydro-Sherbrooke, Hydro-Magog and Hydro-Coaticook customers. See Heat pump rebate. Hydro-Sherbrooke also has its own programs, presented on its website.

What we do for you

We note your utility from the first request, we know each one’s procedures, and we coordinate the shutoff, reconnection or connection so you don’t have to chase two organizations.

Frequently asked questions

I’m in Sherbrooke, but my utility is Hydro-Québec. Is that normal?
Yes. Hydro-Sherbrooke serves part of the city; the rest is served by Hydro-Québec. Your bill says which.
Who do I call during an outage?
The utility named on your bill. For Hydro-Sherbrooke, the official outage page shows the network status and the number to report an outage. A wire on the ground or a burning smell: call 911.
What are the outage numbers in the Eastern Townships?
Hydro-Québec: 1 800 790-2424. Hydro-Sherbrooke: 819 821-5728, 24 hours a day. Hydro-Magog: 819 843-3333 (evenings, 819 843-3334). Hydro-Coaticook: 819 849-6331. Our outage page brings them together, with the online maps.
I’m moving to Sherbrooke: how do I open my account?
If the address is served by Hydro-Sherbrooke, the request is made online or through customer service at 819 821-5622, at least seven business days before the date you want. Otherwise, it’s Hydro-Québec.
How long to connect a new house with Hydro-Sherbrooke?
In a normal situation, seven business days after the subscription request and the work declaration: compliant installation, under 200 A and a connection within 30 m of the network. Beyond that, the Lines Division must be told as early as possible.
Can I get LogisVert as a Hydro-Sherbrooke customer?
Yes. Hydro-Québec’s LogisVert program is open to homeowners, including Hydro-Sherbrooke, Hydro-Magog and Hydro-Coaticook customers. The conditions are in the official guide.
Who submits the request for a new service entrance?
The master electrician. At Hydro-Québec, only CMEQ members can send it the work request; at Hydro-Sherbrooke, the electrician sends the work declaration as soon as the installation is compliant.
Are the rates the same?
Each utility has its own rates and conditions of service. Hydro-Québec’s are in its Conditions of Service, approved by the Régie de l’énergie; Hydro-Sherbrooke’s are published by the City. Your bill tells you which applies.

Sources

About this guide

Written by LTE Électrique, a master electrician’s business in Sherbrooke (RBQ licence 5874-5597-01, CMEQ member). Every rule comes from Québec’s Construction Code or an official source, listed above with the date it was checked. French version reviewed by William Letendre, master electrician, on October 21, 2026.

About us

Cite this guide

To cite this guide, use its title, author and address:

“Hydro-Sherbrooke or Hydro-Québec: who is my utility, and what it changes”, LTE Électrique, https://www.lteelectrique.com/en/guides/hydro-sherbrooke-or-hydro-quebec, French version reviewed by William Letendre, master electrician, on October 21, 2026.

An electrical project?
We call you back the same day.

Call or text 819 570-9836. Free estimate within 24 hours, anywhere in Sherbrooke and the Eastern Townships.

Monday to Friday, 8 a.m. to 4 p.m.

5.0 from 43 Google reviews